1. Foundation Installation: Install the foundation for the water curtain wall according to the construction drawings, including the reinforced concrete foundation and embedded parts. The depth and strength of the reinforced concrete foundation must be designed based on the weight of the wall and usage requirements. The quantity and location of the embedded parts must be accurately installed according to the construction drawings to ensure the stability and safety of the water curtain wall.
2. Steel Frame Installation: Install the steel frame according to the construction drawings. The quantity and dimensions of the steel frame must be designed based on the dimensions of the wall and the requirements of the water spray system. The installation of the steel frame must ensure its flatness and stability.
3. Glass Installation: Install the glass on the steel frame. The quantity and dimensions of the glass must be selected and installed according to the design plan. The installation of the glass must ensure its flatness and airtightness.
4. Water Spray System Installation: Install the water spray system according to the construction drawings. The pipes and pumps of the water spray system must be selected and installed according to the design plan. The installation of the water spray system must ensure its smooth flow and airtightness.
5. Electrical System Installation: Install the electrical system according to the construction drawings. The wiring and equipment of the electrical system must be selected and installed according to the design plan. The installation of the electrical system must ensure its safety and reliability.
6. Commissioning and Acceptance: After the water curtain wall is installed, commissioning and acceptance are required. Commissioning includes checking the water spray effect of the water curtain wall and the operation of the electrical system. Acceptance must be conducted by professionals to ensure that the quality and safety of the water curtain wall meet the requirements.